Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-085-07-23 12-0L77U4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-39-7.1/9.6 ACHS-P039(24) STPF-P039(24) Progress payment No. 009 Payment period ending: 03-02-15 CALIFORNIA PROFESSIONAL ELECTRICAL ENGINEERING 929 OTTERBEIN AVE UNIT E LA PUENTE CA 91748 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 495,864.10 30,935.40 2. a. Extra Work 10,512.00 0.00 b. Adustment Comp. 40,313.00 18,000.00 3. Materials on Hand 4. Earned Subject to Retention 546,689.10 48,935.40 5. Mobilization 5,000.00 0.00 6. Total Work Completed 551,689.10 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 548,689.10 45,935.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,935.40