Dept. of Trans. PROGRESS Serial No. Contract No. 15-296-15-35 12-0L92U4 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 25% Location: Federal Project: 12-ORA-5-0.0/29.6 NHPI-005-2(973) Progress payment No. 003 Payment period ending: 10-20-15 DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 788,345.50 174,058.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 788,345.50 174,058.00 5. Mobilization 180,500.00 0.00 6. Total Work Completed 968,845.50 7. Deductions -18,089.20 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 950,756.30 176,058.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 176,058.00