Dept. of Trans. PROGRESS Serial No. Contract No. 14-356-13-18 12-0L9704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 100% 12-ORA-39-2.1/6.1 Federal Project: HSST-P039(26) Progress payment No. 05 Payment period ending: 12-20-14 TRAFFIC DEVELOPMENT SERVICES 207 W LOS ANGELES AVE MOORPARK CA 93021 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 382,734.05 214,756.70 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 382,734.05 214,756.70 5. Mobilization 20,000.00 1,000.00 6. Total Work Completed 402,734.05 7. Deductions -58,900.00 -58,900.00 8. a.Contract Retentions b. Unsatisfactory Prog. -31,106.82 -21,475.67 c. Reduction after 95% Comp. 9. Total pay to Contractor 312,727.23 135,381.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 135,381.03