Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-14-55 12-0M0904 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 61% Location: Federal Project: 12-ORA-74-0.1/1.8 NONE Progress payment No. 009 Payment period ending: 11-20-20 HIGHLAND CONSTRUCTION INC 133 N PIXLEY ST ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,467,926.65 2,380.00 2. a. Extra Work 24,274.83 0.00 b. Adustment Comp. 9,917.66 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,502,119.14 2,380.00 5. Mobilization 89,000.00 0.00 6. Total Work Completed 1,591,119.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,591,119.14 2,380.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,380.00