Dept. of Trans. PROGRESS Serial No. Contract No. 16-147-13-22 12-0M1204 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 23% Location: Federal Project: 12-ORA-5-28.3/28.6 NONE Progress payment No. 004 Payment period ending: 05-20-16 BMC ENTERPRISES,INC 14510 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 402,157.35 70,699.54 2. a. Extra Work 106,861.00 106,861.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 509,018.35 177,560.54 5. Mobilization 80,000.00 4,000.00 6. Total Work Completed 589,018.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 589,018.35 181,560.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 181,560.54