Dept. of Trans. FINAL Serial No. Contract No. 16-285-15-50 12-0M1204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-5-28.3/28.6 NONE Progress payment No. 008 Payment period ending: 08-16-16 BMC ENTERPRISES,INC 14510 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 768,492.47 0.00 2. a. Extra Work 149,615.06 6,534.26 b. Adustment Comp. -14,800.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 903,307.53 6,534.26 5. Mobilization 80,000.00 0.00 6. Total Work Completed 983,307.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 983,307.53 6,534.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,534.26