Dept. of Trans. PROGRESS Serial No. Contract No. 17-082-10-12 12-0M3404 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 44% Location: Federal Project: 12-ORA-73-16.4/16.6 HSNH-PG P073-114(E) Progress payment No. 007 Payment period ending: 03-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 268,716.34 18,450.00 2. a. Extra Work 53,360.37 19,638.40 b. Adustment Comp. 3. Materials on Hand 46,409.94 -0.02 4. Earned Subject to Retention 368,486.65 38,088.38 5. Mobilization 135,000.00 0.00 6. Total Work Completed 457,076.71 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 501,486.65 36,088.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,088.38