Dept. of Trans. PROGRESS Serial No. Contract No. 17-332-07-07 12-0M3404 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 94% Location: Federal Project: 12-ORA-73-16.4/16.6 HSNH-PG P073-114(E) Progress payment No. 015 Payment period ending: 11-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,368,508.82 138,303.75 2. a. Extra Work 66,647.86 4,713.57 b. Adustment Comp. 3. Materials on Hand 23,788.16 -22,621.78 4. Earned Subject to Retention 1,458,944.84 120,395.54 5. Mobilization 180,000.00 0.00 6. Total Work Completed 1,615,156.68 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions -36,962.95 -12,039.55 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,599,981.89 108,355.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,355.99