Dept. of Trans. PROGRESS Serial No. Contract No. 17-024-09-10 12-0M4004 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 79% Location: Federal Project: 12-ORA-91-0.0/2.8 NHP-P091(143) Progress payment No. 006 Payment period ending: 01-20-17 DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 535,948.75 50,659.08 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 535,948.75 50,659.08 5. Mobilization 64,000.00 0.00 6. Total Work Completed 599,948.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 599,948.75 50,659.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,659.08