Dept. of Trans. PROGRESS Serial No. Contract No. 19-323-13-54 12-0M4804 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 95% Location: Federal Project: 12-ORA-57-16.2/21.2 ACNH-P057(66) Progress payment No. 004 Payment period ending: 11-20-19 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 682,478.67 245,471.67 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 682,478.67 245,471.67 5. Mobilization 16,000.00 800.00 6. Total Work Completed 698,478.67 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 698,478.67 246,271.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 246,271.67