Dept. of Trans. PROGRESS Serial No. Contract No. 18-296-11-00 12-0M4904 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 100% Location: Federal Project: 12-ORA-5-1.2/2.2 HSNH-PI 005-1(635) Progress payment No. 022 Payment period ending: 10-20-18 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,328,208.87 198,389.54 2. a. Extra Work 278,131.77 18,958.81 b. Adustment Comp. 79,245.11 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,685,585.75 217,348.35 5. Mobilization 875,000.00 0.00 6. Total Work Completed 10,560,585.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,560,585.75 217,348.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 217,348.35