Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-09-28 12-0M5004 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 20% Location: Federal Project: 12-ORA-55-1.2/R17.9 ACHS-NHP0-5(505) Progress payment No. 006 Payment period ending: 09-20-17 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,203,616.75 424,630.68 2. a. Extra Work 203,283.64 149,378.05 b. Adustment Comp. 3. Materials on Hand 299,970.50 -4,665.23 4. Earned Subject to Retention 1,706,870.89 569,343.50 5. Mobilization 825,000.00 0.00 6. Total Work Completed 2,231,900.39 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,531,870.89 569,343.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 569,343.50