Dept. of Trans. FINAL Serial No. Contract No. 20-093-09-37 12-0M5004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-55-1.2/R17.9 ACHS-NHP0-5(505) Progress payment No. 039 Payment period ending: 12-20-19 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,663,781.17 0.00 2. a. Extra Work 3,405,894.60 0.00 b. Adustment Comp. 850,315.62 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,919,991.39 0.00 5. Mobilization 1,100,000.00 0.00 6. Total Work Completed 13,019,991.39 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,019,991.39 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00