Dept. of Trans. PROGRESS Serial No. Contract No. 17-144-10-31 12-0M6104 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 12% Location: Federal Project: 12-ORA-91-8.9/16.0 ACHS-NHX0-5(907) Progress payment No. 001 Payment period ending: 05-20-17 POWELL CONSTRUCTORS 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 433,621.00 433,621.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 94,621.14 94,621.14 4. Earned Subject to Retention 528,242.14 528,242.14 5. Mobilization 307,500.00 307,500.00 6. Total Work Completed 741,121.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 835,742.14 835,742.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 835,742.14