Dept. of Trans. PROGRESS Serial No. Contract No. 14-356-12-44 12-0M7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 92% 12-ORA-241-17.3/25.0 Federal Project: NH-P241(4) Progress payment No. 05 Payment period ending: 12-20-14 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,255,357.37 236,229.62 2.a. Extra Work 750.00 750.00 b. Adjustment Comp. -103,466.72 -103,466.72 3. Materials on Hand 4. Earned Subject to Retention 3,152,640.65 133,512.90 5. Mobilization 100,000.00 0.00 6. Total Work Completed 3,252,640.65 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,247,640.65 133,512.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 133,512.90