Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-029-13-42 12-0M7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-241-17.3/25.0 Federal Project: NH-P241(4) Progress payment No. 06 Payment period ending: 01-20-15 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,398,779.80 143,422.43 2.a. Extra Work 750.00 0.00 b. Adjustment Comp. -103,466.72 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,296,063.08 143,422.43 5. Mobilization 100,000.00 0.00 6. Total Work Completed 3,396,063.08 7. Deductions -5,500.00 -500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,390,563.08 142,922.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 142,922.43