Dept. of Trans. PROGRESS Serial No. Contract No. 16-116-13-37 12-0M7204 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 100% Location: Federal Project: 12-ORA-0-7.8/9.9 NHP-X059(58) Progress payment No. 015 Payment period ending: 04-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614-5706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,331,191.07 203,342.00 2. a. Extra Work 52,063.52 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,383,254.59 203,342.00 5. Mobilization 160,000.00 0.00 6. Total Work Completed 2,543,254.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,543,254.59 203,342.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 203,342.00