Dept. of Trans. PROGRESS Serial No. Contract No. 15-113-08-54 12-0M7304 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 62% Location: Federal Project: 12-ORA-5-5.0/34.0 NONE Progress payment No. 002 Payment period ending: 04-20-15 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 92711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 553,930.88 251,439.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 553,930.88 251,439.40 5. Mobilization 40,000.00 2,000.00 6. Total Work Completed 593,930.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 593,930.88 253,439.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 253,439.40