Dept. of Trans. PROGRESS Serial No. Contract No. 21-263-14-18 12-0M9004 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 74% Location: Federal Project: 12-ORA-22-R5.6/R10.9 HSNH-P022(25) Progress payment No. 026 Payment period ending: 09-20-21 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,278,300.50 49,773.75 2. a. Extra Work 561,270.13 116,221.48 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,839,570.63 165,995.23 5. Mobilization 950,000.00 0.00 6. Total Work Completed 11,789,570.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,789,570.63 165,995.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 165,995.23