Dept. of Trans. FINAL Serial No. Contract No. 18-089-08-30 12-0N0404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-91-7.5/18.9 NONE Progress payment No. 017 Payment period ending: 08-30-17 R J NOBLE COMPANY PO BOX 620 ORANGE CA 92856 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,226,701.59 0.00 2. a. Extra Work 435,662.38 0.00 b. Adustment Comp. 578,278.71 19,112.36 3. Materials on Hand 4. Earned Subject to Retention 12,240,642.68 19,112.36 5. Mobilization 280,000.00 0.00 6. Total Work Completed 12,520,642.68 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,520,642.68 21,112.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,112.36