Dept. of Trans. PROGRESS Serial No. Contract No. 17-082-08-35 12-0N0704 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 54% Location: Federal Project: 12-ORA-0 HSNH-P X059-072E Progress payment No. 007 Payment period ending: 03-20-17 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,269,753.34 14,840.00 2. a. Extra Work 195,783.29 9,330.58 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,465,536.63 24,170.58 5. Mobilization 227,000.00 0.00 6. Total Work Completed 1,692,536.63 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,692,536.63 34,170.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,170.58