Dept. of Trans. PROGRESS Serial No. Contract No. 18-331-13-54 12-0N0804 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 41% Location: Federal Project: 12-ORA-5-33.3/34.5 ACNH-X059(75) Progress payment No. 007 Payment period ending: 11-20-18 ACCU CONSTRUCTION INC 2098 S GRAND AVE #A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,051,698.30 324,634.86 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 268,105.25 -6,396.82 4. Earned Subject to Retention 1,319,803.55 318,238.04 5. Mobilization 152,000.00 0.00 6. Total Work Completed 1,203,698.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,471,803.55 318,238.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 318,238.04