Dept. of Trans. PROGRESS Serial No. Contract No. 19-085-15-04 12-0N0804 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 60% Location: Federal Project: 12-ORA-5-33.3/34.5 ACNH-X059(75) Progress payment No. 011 Payment period ending: 03-20-19 ACCU CONSTRUCTION INC 2098 S GRAND AVE #A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,151,736.15 308,939.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 134,363.96 -11,765.21 4. Earned Subject to Retention 2,286,100.11 297,174.19 5. Mobilization 160,000.00 0.00 6. Total Work Completed 2,311,736.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,446,100.11 297,174.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,174.19