Dept. of Trans. PROGRESS Serial No. Contract No. 19-169-08-16 12-0N0804 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 78% Location: Federal Project: 12-ORA-5-33.3/34.5 ACNH-X059(75) Progress payment No. 014 Payment period ending: 06-20-19 ACCU CONSTRUCTION INC 2098 S GRAND AVE #A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,855,176.29 339,723.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 77,928.51 -56,435.45 4. Earned Subject to Retention 2,933,104.80 283,287.95 5. Mobilization 160,000.00 0.00 6. Total Work Completed 3,015,176.29 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,093,104.80 283,287.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 283,287.95