Dept. of Trans. PROGRESS Serial No. Contract No. 17-205-13-34 12-0N1104 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 40% Location: Federal Project: 12-ORA-133-9.5/9.5 NHP-X059(64) Progress payment No. 014 Payment period ending: 07-20-17 USS CAL BUILDERS INC 8051 MAIN ST STANTON CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,507,920.02 629,421.82 2. a. Extra Work 394,594.55 0.00 b. Adustment Comp. 339,689.84 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,242,204.41 629,421.82 5. Mobilization 685,000.00 0.00 6. Total Work Completed 10,927,204.41 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,917,204.41 629,421.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 629,421.82