Dept. of Trans. PROGRESS Serial No. Contract No. 17-058-10-19 12-0N2504 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 37% Location: Federal Project: 12-ORA-405-13.7/22.5 HSNH-P X059-071(E) Progress payment No. 004 Payment period ending: 02-20-17 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 134,539.77 20,916.92 2. a. Extra Work 17,259.25 7,542.46 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 151,799.02 28,459.38 5. Mobilization 63,750.00 0.00 6. Total Work Completed 215,549.02 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 205,549.02 18,459.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,459.38