Dept. of Trans. PROGRESS Serial No. Contract No. 19-266-07-23 12-0N3004 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 88% Location: Federal Project: 12-ORA-241-18.3/18.7 HSST-P241(6) Progress payment No. 005 Payment period ending: 09-20-19 BEADOR CONSTRUCTION COMPANY 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 807,541.30 248,602.50 2. a. Extra Work 9,177.16 9,177.16 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 816,718.46 257,779.66 5. Mobilization 90,000.00 0.00 6. Total Work Completed 906,718.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 906,718.46 257,779.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 257,779.66