Dept. of Trans. FINAL Serial No. Contract No. 20-028-14-04 12-0N3004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-241-18.3/18.7 HSST-P241(6) Progress payment No. 008 Payment period ending: 10-22-19 BEADOR CONSTRUCTION COMPANY 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 859,002.35 0.00 2. a. Extra Work 49,663.49 24,982.87 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 908,665.84 24,982.87 5. Mobilization 90,000.00 0.00 6. Total Work Completed 998,665.84 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 998,665.84 24,982.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,982.87