Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-257-10-42 12-0N3204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-91-R9.8/R18.9 ACNH-P091(148) Progress payment No. 028 Payment period ending: 06-29-22 ACME CONCRETE PAVING INC 4124 E BROADWAY AVE SPOKANE WA 99202 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,013,747.05 0.00 2. a. Extra Work 869,659.03 220,119.44 b. Adustment Comp. 38,714.95 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,922,121.03 220,119.44 5. Mobilization 240,000.00 0.00 6. Total Work Completed 10,162,121.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,162,121.03 220,119.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 220,119.44