Dept. of Trans. PROGRESS Serial No. Contract No. 17-143-08-50 12-0N3604 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 29% Location: Federal Project: 12-ORA-91-R1.0/R5.4 HSNH-P P091-144E Progress payment No. 003 Payment period ending: 05-20-17 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 222,885.00 149,300.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 98,812.88 98,812.88 4. Earned Subject to Retention 321,697.88 248,112.88 5. Mobilization 99,750.00 47,250.00 6. Total Work Completed 322,635.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 421,447.88 295,362.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 295,362.88