Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-081-10-37 12-0N3604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-91-R1.0/R5.4 HSNH-P P091-144E Progress payment No. 011 Payment period ending: 02-14-18 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,162,200.80 495.00 2. a. Extra Work 43,066.74 2,915.44 b. Adustment Comp. 11,883.44 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,217,150.98 3,410.44 5. Mobilization 105,000.00 0.00 6. Total Work Completed 1,322,150.98 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,322,150.98 3,410.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,410.44