Dept. of Trans. PROGRESS Serial No. Contract No. 23-206-09-38 12-0N49A4 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 83% Location: Federal Project: 12-ORA-91-R12.5/R13.9 NONE Progress payment No. 002 Payment period ending: 07-20-23 AWI BUILDERS INC 7831 PARAMOUNT PICO RIVERA CA 90660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 413,865.00 251,078.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 413,865.00 251,078.10 5. Mobilization 6. Total Work Completed 413,865.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 413,865.00 251,078.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 251,078.10