Dept. of Trans. PROGRESS Serial No. Contract No. 16-055-13-29 12-0N5404 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 4% Location: Federal Project: 12-ORA-405-8.4/8.4 BRNH-PI 405-2978(101) Progress payment No. 002 Payment period ending: 02-20-16 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 292,389.65 256,629.65 2. a. Extra Work 776.05 776.05 b. Adustment Comp. 3. Materials on Hand 278,332.50 0.00 4. Earned Subject to Retention 571,498.20 257,405.70 5. Mobilization 455,000.00 455,000.00 6. Total Work Completed 748,165.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,026,498.20 712,405.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 712,405.70