Dept. of Trans. PROGRESS Serial No. Contract No. 17-360-10-58 12-0N5904 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 65% Location: Federal Project: 12-ORA-39-11.6/12.6 ACHS-NHPP-0(390) Progress payment No. 009 Payment period ending: 12-20-17 YAKAR 689 EAST SAN BERNARDINO RD COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 626,732.00 9,880.00 2. a. Extra Work 21,700.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 648,432.00 9,880.00 5. Mobilization 30,000.00 0.00 6. Total Work Completed 678,432.00 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 676,432.00 9,880.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,880.00