Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-103-07-45 12-0N5904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-39-11.6/12.6 ACHS-NHPP-0(390) Progress payment No. 012 Payment period ending: 03-29-18 YAKAR 689 EAST SAN BERNARDINO RD COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 635,682.00 4,150.00 2. a. Extra Work 33,657.52 11,957.52 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 669,339.52 16,107.52 5. Mobilization 30,000.00 0.00 6. Total Work Completed 699,339.52 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 699,339.52 18,107.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,107.52