Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 21-033-14-00 12-0N7204 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 3% Location: Federal Project: 12-ORA-73-10.0/R28.0 HSNH-P073(141) Progress payment No. 003 Payment period ending: 01-20-21 SPECTRUM CONSTRUCTION GROUP INC 16 GOODYEAR #140 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 377,399.94 133,900.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 377,399.94 133,900.00 5. Mobilization 6. Total Work Completed 377,399.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 377,399.94 133,900.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 133,900.00