Dept. of Trans. PROGRESS Serial No. Contract No. 24-110-11-20 12-0N72A4 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 77% Location: Federal Project: 12-ORA-73-10.0/R28.0 HSNH-P073(141) Progress payment No. 015 Payment period ending: 04-20-24 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,454,922.65 343,794.67 2. a. Extra Work 2,940,181.92 235,508.96 b. Adustment Comp. 3. Materials on Hand 695,306.00 -9,650.00 4. Earned Subject to Retention 15,090,410.57 569,653.63 5. Mobilization 1,800,000.00 0.00 6. Total Work Completed 16,195,104.57 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,870,410.57 569,653.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 569,653.63