Dept. of Trans. PROGRESS Serial No. Contract No. 21-053-14-34 12-0N8504 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 56% Location: Federal Project: 12-ORA-1-24.8/32.7 HSNH-P001(661) Progress payment No. 005 Payment period ending: 02-20-21 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 464,507.18 173,817.00 2. a. Extra Work b. Adustment Comp. 6,980.44 504.44 3. Materials on Hand 101,798.59 -2,492.31 4. Earned Subject to Retention 573,286.21 171,829.13 5. Mobilization 14,250.00 0.00 6. Total Work Completed 485,737.62 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 577,536.21 171,829.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 171,829.13