Dept. of Trans. PROGRESS Serial No. Contract No. 25-056-10-58 12-0N8904 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 42% Location: Federal Project: 12-ORA-133-8.3/M9.3 ACNH-P133(19) Progress payment No. 015 Payment period ending: 02-20-25 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,291,568.36 1,826,994.16 2. a. Extra Work 156,465.73 38,186.00 b. Adustment Comp. 3. Materials on Hand 260,697.68 165,930.75 4. Earned Subject to Retention 11,708,731.77 2,031,110.91 5. Mobilization 2,120,000.00 106,000.00 6. Total Work Completed 13,568,034.09 7. Deductions -22,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,806,731.77 2,127,110.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,127,110.91