Dept. of Trans. PROGRESS Serial No. Contract No. 22-049-13-57 12-0N9204 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 0% Location: Federal Project: 12-ORA-22-R9.1/R9.1 NONE Progress payment No. 003 Payment period ending: 02-20-22 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 54,109.51 2,270.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 54,109.51 2,270.00 5. Mobilization 40,000.00 0.00 6. Total Work Completed 94,109.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 94,109.51 2,270.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,270.00