Dept. of Trans. PROGRESS Serial No. Contract No. 22-143-15-19 12-0N9204 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 36% Location: Federal Project: 12-ORA-22-R9.1/R9.1 NONE Progress payment No. 006 Payment period ending: 05-20-22 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 291,425.99 146,948.84 2. a. Extra Work 86,818.81 22,340.91 b. Adustment Comp. 29,050.45 29,050.45 3. Materials on Hand 4. Earned Subject to Retention 407,295.25 198,340.20 5. Mobilization 76,000.00 0.00 6. Total Work Completed 483,295.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 483,295.25 198,340.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 198,340.20