Dept. of Trans. PROGRESS Serial No. Contract No. 20-022-13-14 12-0N9304 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 35% Location: Federal Project: 12-ORA-1-20.4/21.0 NONE Progress payment No. 002 Payment period ending: 01-20-20 BOSCO CONSTRUCTORS INC 21353 MAYALL ST CHATSWORTH CA 91311 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 167,558.86 13,516.03 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 167,558.86 13,516.03 5. Mobilization 53,868.59 0.00 6. Total Work Completed 221,427.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 221,427.45 13,516.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,516.03