Dept. of Trans. PROGRESS Serial No. Contract No. 20-357-12-55 12-0P0904 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 17% Location: Federal Project: 12-ORA-5-10.3/10.3 NONE 12-ORA-5-23.2/23.2 Progress payment No. 003 Payment period ending: 12-20-20 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 251,159.00 65,602.50 2. a. Extra Work 1,139.81 1,139.81 b. Adustment Comp. 3. Materials on Hand 31,149.29 31,149.29 4. Earned Subject to Retention 283,448.10 97,891.60 5. Mobilization 71,250.00 0.00 6. Total Work Completed 323,548.81 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 354,698.10 97,891.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,891.60