Dept. of Trans. PROGRESS Serial No. Contract No. 21-055-10-13 12-0P0904 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 30% Location: Federal Project: 12-ORA-5-10.3/10.3 NONE 12-ORA-5-23.2/23.2 Progress payment No. 005 Payment period ending: 02-20-21 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 537,949.50 208,052.00 2. a. Extra Work 8,279.20 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -31,149.29 4. Earned Subject to Retention 546,228.70 176,902.71 5. Mobilization 75,000.00 3,750.00 6. Total Work Completed 621,228.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 621,228.70 180,652.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 180,652.71