Dept. of Trans. PROGRESS Serial No. Contract No. 17-173-10-03 12-0P2504 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 86% Location: Federal Project: 12-ORA-405-3.7/3.9 NONE Progress payment No. 007 Payment period ending: 06-20-17 BMC ENTERPRISES,INC 14510 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 824,848.65 20,943.17 2. a. Extra Work 13,966.58 0.00 b. Adustment Comp. 7,325.77 0.00 3. Materials on Hand 4. Earned Subject to Retention 846,141.00 20,943.17 5. Mobilization 83,000.00 0.00 6. Total Work Completed 929,141.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 929,141.00 20,943.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,943.17