Dept. of Trans. PROGRESS Serial No. Contract No. 21-117-12-07 12-0P4004 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 16% Location: Federal Project: 12-ORA-405-5.6/5.6 SIMG-405-2(13) Progress payment No. 002 Payment period ending: 04-20-21 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 202,079.18 81,267.85 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 112,153.58 112,153.58 4. Earned Subject to Retention 314,232.76 193,421.43 5. Mobilization 114,000.00 24,000.00 6. Total Work Completed 316,079.18 7. Deductions -6,303.38 -1,327.03 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 421,929.38 216,094.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 216,094.40