Dept. of Trans. PROGRESS Serial No. Contract No. 21-235-15-00 12-0P4004 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 57% Location: Federal Project: 12-ORA-405-5.6/5.6 SIMG-405-2(13) Progress payment No. 006 Payment period ending: 08-20-21 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 760,097.75 86,080.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 760,097.75 86,080.20 5. Mobilization 120,000.00 0.00 6. Total Work Completed 880,097.75 7. Deductions -6,635.14 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 873,462.61 86,080.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 86,080.20