Dept. of Trans. PROGRESS Serial No. Contract No. 23-360-13-39 12-0P42U4 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 83% Location: Federal Project: 12-ORA-5-0.6/43.0 ACNH-X059(83) 12-ORA-22-0.0/R13.2 12-ORA-55-0.6/G17.2 Progress payment No. 034 Payment period ending: 12-20-23 INTERNATIONAL LINE BUILDERS, INC. PO BOX 3039 RIVERSIDE CA 92519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,972,397.38 199,357.92 2. a. Extra Work 321,772.38 82,043.05 b. Adustment Comp. 1,063,294.34 0.00 3. Materials on Hand 1,931,754.00 0.00 4. Earned Subject to Retention 14,289,218.10 281,400.97 5. Mobilization 309,702.21 0.00 6. Total Work Completed 12,667,166.31 7. Deductions -50,000.00 40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,548,920.31 321,400.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 321,400.97