Dept. of Trans. PROGRESS Serial No. Contract No. 24-295-11-35 12-0P42U4 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 95% Location: Federal Project: 12-ORA-5-0.6/43.0 ACNH-X059(83) 12-ORA-22-0.0/R13.2 12-ORA-55-0.6/G17.2 Progress payment No. 044 Payment period ending: 10-20-24 INTERNATIONAL LINE BUILDERS, INC. PO BOX 3039 RIVERSIDE CA 92519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,848,018.03 216,511.55 2. a. Extra Work 757,616.24 8,331.68 b. Adustment Comp. 1,233,079.07 133,054.37 3. Materials on Hand 300,157.00 -126,648.00 4. Earned Subject to Retention 16,138,870.34 231,249.60 5. Mobilization 309,702.21 0.00 6. Total Work Completed 16,148,415.55 7. Deductions -80,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,368,572.55 221,249.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 221,249.60