Dept. of Trans. PROGRESS Serial No. Contract No. 17-173-12-19 12-0P4504 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 93% Location: Federal Project: 12-ORA-57-11.0/22.5 NHP-P057(63) Progress payment No. 012 Payment period ending: 06-20-17 AUTOBAHN CONSTRUCTION, INC PO BOX 11238 SANTA ANA CA 92711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,030,083.05 192,424.05 2. a. Extra Work 130,553.99 9,916.36 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,160,637.04 202,340.41 5. Mobilization 350,000.00 0.00 6. Total Work Completed 4,510,637.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,510,637.04 202,340.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,340.41